Interconnection queue status: third quarter 2026
This quarterly update reports the number and capacity of active interconnection requests in the Midland Grid queue, and the average time from request to executed interconnection agreement for agreements signed in the past twelve months. Standalone battery storage is reported separately because it is now the largest resource type in the queue.
Queue by resource type
| Resource type | Requests | GW | Share | Signed, 12 mo. | Avg. wait, mo. |
|---|---|---|---|---|---|
| Battery storage (standalone) | 214 | 41.6 | 33% | 23 | 34 |
| Solar | 176 | 30.2 | 24% | 17 | 36 |
| Solar plus storage | 138 | 27.9 | 22% | 14 | 37 |
| Wind | 61 | 14.8 | 12% | 5 | 39 |
| Natural gas | 22 | 9.4 | 7% | 4 | 28 |
| Other | 15 | 3.1 | 2% | 2 | 30 |
| All resource types | 626 | 127.0 | 100% | 65 | 35 |
Requests: active requests, meaning valid requests without an executed interconnection agreement. GW: requested capacity. Signed, 12 mo.: agreements executed in the past twelve months. Average wait covers the 65 agreements executed between October 1, 2025 and September 30, 2026, measured from the date the request was deemed valid. “Other” includes hydro, geothermal and merchant transmission.
Standalone storage
Standalone storage requests in the queue rose to 214, with 41.6 GW of requested capacity, from 178 requests and 33.0 GW a year earlier. The 23 storage agreements executed in the past twelve months, covering 4.4 GW, waited an average of 34 months from request to agreement. Two years ago the comparable figure was 27 months.
| As of | Requests | GW | Signed, 12 mo. | Withdrawn, 12 mo. | Avg. wait, mo. |
|---|---|---|---|---|---|
| Sep 30, 2024 | 141 | 24.3 | 15 | 22 | 27 |
| Sep 30, 2025 | 178 | 33.0 | 19 | 27 | 31 |
| Sep 30, 2026 | 214 | 41.6 | 23 | 31 | 34 |
| Study phase | Requests | GW |
|---|---|---|
| Phase 1 cluster study | 96 | 18.9 |
| Phase 2 cluster study | 61 | 12.2 |
| Facilities study | 38 | 7.1 |
| Agreement in negotiation | 19 | 3.4 |
| Total | 214 | 41.6 |
Withdrawn, 12 mo.: storage requests withdrawn in the prior twelve months. Capacity is requested injection capacity in GW. Midland Grid does not collect storage energy capacity (MWh) through the interconnection process.
Study process during the quarter
Phase 2 results for the 2025 cluster were issued in August. Withdrawals after Phase 1 triggered restudies for two subgroups of that cluster, and Midland Grid completed both restudies within the quarter. The 2026 cluster request window closed on June 30, 2026 with 58 new standalone storage requests totaling 11.4 GW. Phase 1 studies for that cluster are under way.
Network upgrades identified in studies remain the main driver of wait times. Requests at substations in the western part of the footprint, where solar and storage requests are concentrated, carry the highest upgrade cost allocations and the longest study times.
Definitions
- Average wait to agreement
- Mean time from the date a request was deemed valid to the date its interconnection agreement was executed, for agreements executed in the twelve months to the reporting date. It does not include time after the agreement for construction, network upgrades or energization.
- Active request
- A valid request that has not withdrawn and has not executed an interconnection agreement.
- Requested capacity
- The maximum injection capacity in the request, in GW. Solar plus storage requests are counted once at their combined injection limit.
Questions about this report: Interconnection Planning, interconnection@midlandgrid.example. Request-level queue data is available to registered stakeholders through the stakeholder portal.